Client team works through the staging site, testing all functionality and beginning CMS content entry. Bugs, issues, and feedback are logged centrally for Phosphor to review.
02
Bug Fixes & Remediation 4 days
Phosphor
Fri 3 Jul → Wed 8 Jul
Phosphor development team works through the UAT issue log, prioritising critical bugs and functional fixes before the final content phase begins.
03
Final Content Upload + Feedback 6 days
Masport
Thu 9 Jul → Thu 16 Jul
Client completes all remaining content population across the site. Final round of feedback submitted to Phosphor — focus on content accuracy, presentation, and any outstanding visual adjustments.
04
Final Bug Fixes 2 days
Phosphor
Fri 17 Jul → Mon 20 Jul
Phosphor addresses any remaining issues raised during the final feedback round. No new scope — fixes only. Site is stabilised and prepared for client review.
05
Client Approval + Go/No Go 2 days
Masport
Tue 21 Jul → Wed 22 Jul
Client does a final review of the site in full and provides written sign-off. Go/no go decision confirmed by end of day Wednesday. Any blockers raised here must be critical only.
06
Go Live Prep 2 days
Phosphor
Thu 23 Jul → Fri 24 Jul
Phosphor runs final pre-launch checks — DNS configuration, redirects, performance review, and deployment steps. Site is staged and ready to flip live on Monday.
07
Go Live
Phosphor
Monday 27 July 2026
Site goes live. Hard deadline 29 July — 2 days of buffer remaining.